150 T/month Oxidation Production Line and Max Profile Length 6500mm
一. Product Description:
1.An anodizing production line should have proper ventilation to control fumes and ensure a safe working environment.
2.A mini anodizing production line may have inspection stations or quality control measures to verify the quality of the anodized parts.
3.Anodizing processes involve working with hazardous chemicals and electrical currents.
二. Design Condition
1 | Alloy | Aluminum 6061 to 6063 or others |
2 | Anodizing film thinkness | 10~ 12µm micron |
3 | Average coverage area | 400m²/T (ton) |
4 | Max aluminium profile length | 6500mm |
5 | Extrusion ratio | 2.5kg/m² |
6 | Working hour/m | 300d/m x 20h/d = 600h/m |
7 | Racking system | Two fixtures /rack |
8 | Racking operation | Manual |
9 | Equipment Usage Rate | 0.9 |
10 | Power supply | AC 3phase 380v 50hz |
11 | Control Power | AC220V 50Hz |
12 | Water supply | 2kg/cm²·G |
13 | Hot steam | 6kg/cm²·G |
14 | Compressor air | 6kg/cm²· G |
三.Process Tank
四.Treatment Process:
(6) Average anodizing layer : 0.36*1.3*30*0.77 =10.81um
1) Clour process: Mix Salts
2) Quantity:2 jig(rack)/tank x 1tanks = 2jig(rack)
3) Current density: 70A
4) Process time: 2-8min
6. Sealing
1) Sealing menthod: Sealing at Medium or Normal Temperature
2) Quantity:6jig(rack)/tank x 1 tank
3) Process time 10-15min
五. Design Parameter and Setting
1. Anodizing treatment area:
1) Each anodizing process tank need 40min ,where total jig(rack)/year:
( 2 rack x 1 tank x 60min/h) ÷40min x600 hour =1800jig(rack)
2) Design 42.9m²/jig(rack) . Where every tank is 85.8m²
3) Area treatment/year : 1800jig(rack)x 42.9m² /jig =77220m²
2. Anodizing treatment weight:
Monthly output : 77220m²÷400m²/T*0.9=174T≧150T
3. Power consumption:
1) Anodising Tank:100m²/tank* 130A/ m²÷0.9=14444A/tank
Power Rectifier : 15000A =1unit
2) Clouring tank: 100㎡/tank×70A/m²÷0.9 = 7777A/tank
Colour Rectifier : 8000A =1 unit
六. Process Chat
Discription for Un
1) De = Degreasing
2) Rs = Rinsing, HW Rs = Hot Water Rinsing
4) AE = Alkaline Etching
5) Ne = Neutralization
6) An = Anodizing
7) Cl = Coloring
8) Sl = Sealing
9) MU = Material Unloading
10) Pc = Packing